Best engineers team for Solar Panel Maintenance & Service in Rajasthan
Scope of Solar Panel Services and Procedure
The scope of O & M is for trouble free operation of the power plant to ensure that maximum solar energy is fed to the grid. Following activities are envisaged as part of O & M:
- Trouble free operation of the Power Plant.
- Ensure that the Power Generated is pumped to Grid without any problem.
- Monitor the Performance of the Power Plant by data logging.
- Monthly report preparation & reporting to Customer on performance of Power Plant.
- Maintenance of Module – Periodic cleaning of 1 MW Solar PV Modules
- Scheduled maintenance of Inverter, LT, and HT & Transformer.
- Attend the emergency break down of the components.
- Frequent testing of plant equipment by ‘Walk Down’ checks the internal condition of equipment such as module performance, inverter efficiency test, monitoring system testing etc.
- Careful logging of operation data and periodically processing it to determine abnormal or slowly deteriorating conditions.
- Careful control and supervision of operating conditions. (Wide and rapid variations in voltage and frequency conditions do contribute to increased maintenance).
- Regulate routine maintenance work such as housekeeping of plant area, keeping equipment clean, cleaning of modules, proper maintenance of inverters etc.
- Spare parts and inventory maintenance.
- Proper codification of all spares and consumables.
- Spare parts indenting.
- Indenting and maintaining minimum level of critical mandatory and recommended spares.
Are you looking for a Solar Panel Engineers in Jaipur & All over Rajasthan? Process Now! Call @ 911-911-2929 / 91160-98980 .Save your time by registering on our website.
Plant Maintenance Schedule
|
Sl. No.
|
Inspection
|
Actions required
|
Inspection Frequency
|
|
A
|
Solar Modules
|
|
1.
|
Dust deposition
|
Cleaning of modules
|
About 15 Days Average
|
|
2.
|
Module Junction box malfunction, visual inspection
|
Replace the Module in case of failure.
|
1 Month
|
|
3.
|
Improper Module Cable Connectors
|
Replace the Cables / Connectors
|
1 Month
|
|
4.
|
De-lamination, discoloration leading to low output
|
Replace the Module
|
1 Month
|
|
5.
|
Module Cracks
|
Replace the module
|
1 Month
|
|
B
|
Solar Module Mounting Structure
|
|
1.
|
Inspection of Mounting Structure and Hardware
|
Check Fasteners – take remedial measures in case of issues.
Check lugs of earthing conductors for corrosion – change as needed.
|
3 Month
|
|
C
|
Inverter (Input) Technical Parameters
|
|
1.
|
DC Voltage @ Connection Point
|
3 Months
|
|
2.
|
Current @ Connection Point
|
3 Months
|
|
D
|
Inverter
|
|
1.
|
Loose cable Termination
|
Tighten the connection
|
6 Months
|
|
2.
|
Dust Deposition
|
Cleaning
|
Monthly
|
|
3.
|
Cleaning of Air Filters
|
Cleaning
|
Monthly
|
|
4.
|
Performance monitoring
|
Visual
|
Daily
|
|
5.
|
Data Logging
|
|
Daily
|
|
6.
|
Report preparation
|
|
Monthly
|
|
E
|
Inverter (Output) Technical Parameters
|
|
1.
|
Output Voltage
|
3 Months
|
|
2.
|
Current
|
3 Months
|
|
3.
|
Frequency
|
3 Months
|
|
4.
|
Output Power
|
3 Months
|
|
F
|
LT Panel
|
|
1.
|
Loose cable Termination
|
Tighten the connection
|
6 Months
|
|
2.
|
Schedule maintenance as indicated by LV Panel Supplier
|
|
|
3.
|
Dust Deposition
|
Cleaning
|
Monthly
|
|
4.
|
Performance monitoring
|
|
Daily
|
|
G
|
LT Panel (Output) Technical Parameters
|
|
1.
|
Voltage
|
|
Monthly
|
|
2.
|
Current
|
|
Monthly
|
|
3.
|
Frequency
|
|
Monthly
|
|
H
|
Transformer
|
|
1.
|
Schedule maintenance as indicated by Transformer Supplier
|
|
|
2.
|
Dust Deposition
|
Cleaning
|
2 Months
|
|
3.
|
Performance monitoring
|
|
Daily
|
|
I
|
Transformer (Output) Technical Parameters
|
|
1.
|
Voltage
|
|
Monthly
|
|
2.
|
Current
|
|
Monthly
|
|
3.
|
Frequency
|
|
Monthly
|
|
J
|
MV Panel
|
Schedule maintenance as indicated by MV Panel Supplier
|
|
1.
|
Dust Deposition
|
Cleaning
|
3 Months
|
|
2.
|
Performance monitoring
|
|
Daily
|
|
K
|
MV Panel (Output) Technical Parameters
|
|
1.
|
Voltage
|
|
2 Months
|
|
2.
|
Frequency
|
|
2 Months
|
|
L
|
Emergency Break down
|
|
As and When
|
|
M
|
Spare parts
|
Ensure availability of spare parts as required for the plant to run normally.
|
1 Month
|
|
N
|
Irradiance Meter cleaning
|
Cleaning with soft cloth
|
Daily
|
|
O
|
Cable (AC & DC)
|
Visual inspection
|
15 Days
|
|
P
|
SCADA
|
Data Monitoring
|
Daily
|
All periodic maintenance & inspections shall be done as specified by the equipment manufacturers.